APRIL CONSTRUCTION UPDATE: STAGE 4 NEARING COMPLETION 

APRIL CONSTRUCTION UPDATE: STAGE 4 NEARING COMPLETION 
Thursday 18th April by Everley Sunbury
Share

April Construction Update

 

Current progress 

Stages 2 & 3 All construction works are complete and documentation has been approved by referral authorities. Statement of Compliance (SOC) has been requested on multiple occasions; however, Council requires confirmation a s173 Agreement has been registered on title before they will issue SOC. The s173 Agreement has been with the Titles Office for more than a week and registration is expected shortly. Based on typical registration time frames, SOC is expected by the end of April.
Anticipated Title Date: May 2024

Stage 4 Asphalt is complete with final lot levels and topsoiling underway. Works inspections have commenced and documentation is currently being prepared for submission to service authorities. Statement of Compliance is expected in May.
Anticipated Title Date: June 2024

Stage 5 Construction is progressing well with major sewer works complete and drainage underway.
Anticipated Title Date: 4th Quarter 2024

Stage 6 Detailed engineering designs are awaiting final approval by Council.
Anticipated Title Date: 2nd Quarter 2025

If you’re ready to call Sunbury home and build your own dream home at Everley, enquire now, or book an appointment to speak to our friendly sales team.

Our sales office is open 7 days a week at 1 Tanninbrae Drive, Sunbury VIC 3429. Access opposite Goonawarra Golf Course near intersection of Sunbury Rd & Francis Blvd. Call 0499 949 748 for further details.

To discover why Everley is your perfect forever home, fill out the registration form on our website to receive priority access to our launch.

Register Your Details

Join our VIP list and be the first to hear about new releases and project updates.

  • This field is for validation purposes and should be left unchanged.
* Mandatory fields. By registering, I consent to being contacted regarding Everley Sunbury