NOVEMBER CONSTRUCTION UPDATE: FINAL WORKS INSPECTIONS HAVE COMMENCED

NOVEMBER CONSTRUCTION UPDATE: FINAL WORKS INSPECTIONS HAVE COMMENCED
Wednesday 20th December by Everley Sunbury
Share

November Construction Update

 

Current progress 

Stage 2 & Stage 3 Works inspections and submission of the required documentation to service authorities is underway. Final consents to Statement of Compliance are expected in late December and early January. Lodgment with the Titles Office is expected in late January with title release and settlements in February.
Anticipated Title Date: February 2024

Stage 4 Kerb installation is complete with preparations for footpath currently underway. Electrical reticulation and retaining wall construction are well advanced.
Anticipated Title Date: 2nd Quarter 2024

Stage 5 Detailed engineering plans are expected to achieve final approval in early 2024.
Anticipated Title Date: 3rd Quarter 2024

Stage 6 Detailed engineering designs are expected to achieve final approval in early 2024.
Anticipated Title Date: 1st Quarter 2025

If you’re ready to call Sunbury home and build your own dream home at Everley, enquire now, or book an appointment to speak to our friendly sales team. 

Our sales office is open 7 days a week at 1 Tanninbrae Drive, Sunbury VIC 3429. Access opposite Goonawarra Golf Course near intersection of Sunbury Rd & Francis Blvd. Call 0499 949 748 for further details. 

To discover why Everley is your perfect forever home, fill out the registration form on our website to receive priority access to our launch.

Register Your Details

Join our VIP list and be the first to hear about new releases and project updates.

  • This field is for validation purposes and should be left unchanged.
* Mandatory fields. By registering, I consent to being contacted regarding Everley Sunbury