August construction update

Stage 6 settlements expected in
October 2025

Current Progress

Stage 6 Statement of compliance has been issued and we are currently awaiting release certificates to enable lodgment of the plan of subdivision with the Titles Office. Based on typical processing time frames, we are expecting title release and settlements in October.

Title Date: October 2025.

Stage 6F & 6G Drainage and sewer are continuing and retaining wall construction has commenced. Road boxing and pavement subgrade are also underway.

Title Date: 1st Quarter 2026.

 

Disclaimer: All timeframes are provided as a guide only and based on the best information currently available. Delays due to weather, site conditions, and authority approvals often occur and are outside of our control. We will continue to provide updates as new information arises.

 