May 2026 construction update

Stage 7 construction has commenced

Current Progress

Stage 6 House building is continuing, with more than 60 dwellings under construction and nearly 10 having obtained a Certificate of Occupancy.

Title Date: October 2025 – Complete.

 

Stage 6F & 6G Title registration and settlements occurred in late May. Housing construction is expected to commence shortly.

Title Date: May 2026 – Complete.

Stage 7  Stage 7 construction has commenced with top soil stripping nearly complete. Sewer and drainage are expected to commence shortly.

Title Date: 2nd Quarter 2027.

 

Stage 9 The tender process for Stage 9 is continuing. A preferred contractor is expected to be nominated shortly with construction estimated to commence in Q3 2026.

Title Date: 3rd Quarter 2027.

 

Disclaimer: All timeframes are provided as a guide only and based on the best information currently available. Delays due to weather, site conditions, and authority approvals often occur and are outside of our control. We will continue to provide updates as new information arises.

 