May construction update

Stage 6 purchasers should
prepare for settlement

Current Progress

Stage 6 Asphalt, footpaths, driveway crossovers and topsoiling are all complete. Road signage and line marking are underway. Authority inspections will commence this week.

Purchasers in Stage 6 should commence preparations for settlement with their conveyancers and financiers. Advice regarding site access for valuation purposes will be issued shortly.

Title Date: August 2025.

Stage 6F & 6G Final authority approvals have been achieved with construction due to commence in June. Civ2Con has been appointed as the civil contractor that will construct Stages 6F & 6G.

Title Date: 1st Quarter 2026.

 

Disclaimer: All timeframes are provided as a guide only and based on the best information currently available. Delays due to weather, site conditions, and authority approvals often occur and are outside of our control. We will continue to provide updates as new information arises.

 